Project:
|
SPDO Conversion Works at the following sites:-
Deanshanger SPDO
Welford SPDO
Long Buckby SPDO
Syston SPDO
Ravenshead SPDO
Maulden SPDO
|
| |
|
|
Date:
|
2002 onwards to December 2004
|
| |
|
|
Client:
|
Royal Mail Property Holdings
|
| |
Property Department
|
| |
9th Floor
|
| |
86, Lionel Street
|
| |
Birmingham
|
| |
B3 1HQ.
|
| |
|
| |
|
|
Partner in Charge:
|
E. J. Cavanagh / N. Siverns
|
| |
|
|
Client Objectives:
|
·
Refurbishment of rural posting facilities to comply with minimal
health & safety standards.
|
| |
· Improve
the working environment for Royal Mail staff.
|
| |
· Allow
for flat access to the working areas.
|
| |
|
|
Project Values:
|
Deanshanger SPDO - £80 k
Welford SPDO - £30 k
Long Buckby SPDO - £75 k
Syston SPDO - £40 k
Ravenshead SPDO - £30 k
Maulden SPDO - £65 k
|
| |
|
|
ACP Role:
|
This practice was the lead consultant
over a team including:-
|
| |
· M
& E Design and Installation.
|
| |
·
Planning Supervision. |
| |
·
Structural Engineers. |
| |
·
Party Wall Surveyors.
|
| |
|
|
Outcome:
|
Following detailed Feasibility Studies of various options the works
were prepared and executed including:-
|
| |
·
Budget Estimates.
|
| |
·
Schedules of Works
& Contracts
|
| |
·
Working Drawings.
|
| |
·
Building Regulation Approval.
|
| |
·
Planning Permission. |
| |
·
Party Wall Agreements. |
| |
|
|
Generally:
|
The projects were successful and are all complete with the offices
now being used by Royal Mail staff in the rural area.
|
| |
|
|
Tender Documentation:
|
The form of contract used was IFC 84 with Royal Mail amendments
and were subject to single stage selective tendering. In addition,
detailed plans and a schedule of works, incorporating the Engineering
and Security works were prepared.
|
| |
|
|
On Site Period:
|
The works were programmed for both in hours and out of hours periods,
with temporary arrangements agreed with the local Sub Postmaster
and, in some cases, out housing of the Royal Mail staff during the
works.
|
|
Statutory and Other Approvals:
|
The following approvals were sought
and gained:-
|
| |
·
Building Regulation
approval.
|
| |
·
Planning Permission:-
Building alterations.
|
| |
·
Fire Officers
approval.
|
| |
·
Post Office internal
authority process. |
| |
·
Party Wall Agreements.
|
| |
|
|
Post Contract:
|
The works have been completed and have now passed their end of
defects periods and are complete.
|
| |
|