Project:
|
Wheelock Wharf: Canal side Warehouse and Office Development.
|
| |
|
|
Date:
|
November 1996.
|
| |
|
|
Client:
|
British Waterways,
|
| |
Commercial Department,
|
| |
Navigation Road,
|
| |
Northwich,
|
| |
Cheshire,
|
| |
CW8 1BH
|
| |
|
| |
|
|
Partner in Charge:
|
E. J. Cavanagh
|
| |
|
|
Client Objectives:
|
·
To provide a lettable
/ saleable development of a Grade II Listed Building.
|
| |
·
Improve the utilisation
of vacant units.
|
| |
·
Carry out essential maintenance.
|
| |
|
|
Project Value:
|
£ 159K
|
| |
|
|
Consultants Role:
|
This practice was the lead consultant
over a team including:
|
| |
·
Structural Engineer.
|
| |
·
Mechanical & Electrical
Engineer.
|
| |
|
|
Outcome:
|
A detailed Feasibility Study of various
options was prepared including:
|
| |
·
Budget Estimates.
|
| |
·
Brief Schedules of Works.
|
| |
·
Constraints.
|
| |
·
Advantages and Disadvantages.
|
| |
|
|
Generally:
|
The project was successfully completed
in all the objectives of the Client stated above, on time and within
budget.
|
| |
|
|
Tender Documentation:
|
The form of contract used was the IFC
84 (with variations to accommodate British Waterways requirements) and
was subject to single stage selective tendering. In addition, detailed
plans and a schedule of works, incorporating the Engineering and Security
works were prepared using AutoCAD drafting.
|
| |
|
|
On Site Period:
|
The works were programmed for in office
hours periods, with temporary arrangements agreed for adjoining owners
and canal users. Special arrangements had to be agreed with the Local
Authority Conservation Officer on this Listed Building.
|
|
Statutory and Other Approvals:
|
The following approvals were sought
and gained:
|
| |
·
Building Regulation approval.
|
| |
·
Planning Permission: Listed Building Consent.
|
| |
·
Fire Officers approval.
|
| |
·
British Waterways Engineer
approval for working adjacent to the canal.
|
| |
|